Batang Kali-Genting road set to open by May 2024, says Selangor exco

Repair works scheduled to finish in March, says Izham Hashim

2:54 PM MYT

 

SHAH ALAM – The Batang Kali-Genting Highlands road is expected to be open to the public by May next year, as it is scheduled to be completed in March.

Izham Hashim, Selangor’s infrastructure executive councillor, said the slope repair and stabilisation work had reached 38.6% progress so far.

“We started repairing the slopes on May 28, and expect it to be completed on March 29 next year. We will consider reopening the road to Genting Highlands when everything is ready.

“We have also researched the appropriate engineering method, and found that the ‘TerraLink wall system’ design is the most suitable for the conditions of the site (slope), which is quite narrow,” he said, in response to a question from R. Rajiv (Bukit Gasing-DAP) on the status of the Batang Kali landslide tragedy.

In an interview, Izham had previously said that only one lane was currently open, and this was restricted to workers in the Genting Highlands area. 

Deputy Prime Minister Datuk Seri Ahmad Zahid Hamidi had previously said that continuous rainfall was the main trigger for the landslide at the Batang Kali campsite, which killed 31 people last year.

The 2.30am tragedy on December 16 claimed the lives of 31 campers, out of a total of 92 victims, after a landslide buried the Father’s Organic Farm camping area in Batang Kali.

The heartbreaking incident saw 18 adults and 13 children perish, with 20 bodies found in Sector A, one in Sector B and another 10 in Sector C in the camp area. – November 17, 2023

Topics

 

Popular

Rumah agam Sharifah Aini dirobohkan, ada persoal mengapa kerajaan tidak jadikan muzium?

Rumah agam milik biduanita negara, Allahyarham Datuk Sharifah Aini yang selama ini menjadi lambang kemewahan anak seni tempatan yang benar-benar sukses dalam bidang nyanyian sedang dalam proses untuk dirobohkan.

BAM confirms salary increment demands from top players, review process underway

Acting president Datuk V. Subramaniam acknowledges requests for salary increments and emphasises ongoing discussions to assess their feasibility

Mat Sabu says rice supply can last four to five months

There is sufficient rice supply to cover the country’s domestic needs for the next four to five months, said Agriculture and Food Security Minister Datuk Seri Mohamad Sabu.

Related