Ampang-Sri Petaling LRT line service expected to resume Feb 2024: Rapid Rail

This is due to comprehensive repairs required for two flyovers nearby Bandaraya station

6:53 PM MYT

 

KUALA LUMPUR – The Ampang-Sri Petaling LRT line is expected to resume operations on February 29 next year after the comprehensive repair work on the flyover and track structure near the Bandaraya LRT station is completed. 

Rapid Rail Sdn Bhd in a statement today said that the original plan was to complete the repair work and resume operations by the middle of October. However, some other damage was detected on the structure of two nearby flyovers which required comprehensive repair works. 

“After getting views and advice from the consulting engineer, additional work needs to be done on the structure of the flyovers to ensure that they are safe, in line with the required specifications, and are able to meet normal operating criteria. 

“Rapid Rail would like to apologise for the inconvenience caused. The decision to extend the time of the restoration work is to ensure that all damage can be identified and repaired to ensure the safety of commuters,” read the statement.  

On January 27, the LRT service on the Ampang route was delayed due to the kinked track alignment detected near the Bandaraya station. 

Rapid Rail then closed the route between Masjid Jamek station and Bandaraya station for safety purposes, and LRT passengers have had to use alternatives, including buses to continue to their respective destinations. – September 27, 2023

Topics

 

Popular

Rumah agam Sharifah Aini dirobohkan, ada persoal mengapa kerajaan tidak jadikan muzium?

Rumah agam milik biduanita negara, Allahyarham Datuk Sharifah Aini yang selama ini menjadi lambang kemewahan anak seni tempatan yang benar-benar sukses dalam bidang nyanyian sedang dalam proses untuk dirobohkan.

BAM confirms salary increment demands from top players, review process underway

Acting president Datuk V. Subramaniam acknowledges requests for salary increments and emphasises ongoing discussions to assess their feasibility

Mat Sabu says rice supply can last four to five months

There is sufficient rice supply to cover the country’s domestic needs for the next four to five months, said Agriculture and Food Security Minister Datuk Seri Mohamad Sabu.

Related